Saturday, December 02, 2006

Nov 30th - Warm Board - Cold Night



Today Pat, Greenbay and I started and completed the installation of the warm board on the 3rd level loft. The left over warm board was to be used on the original cabin floor but since we needed the warm board in this area to complete the framing, I've decided to use the remaining sheets and scraps up on the 3rd level. It takes some careful planning on my part and after making a sketch we are able to complete the entire 3rd level with only 1/2 a sheet of warm board remaining. I stay a bit later to figure how I will route the lines on the floor. It's a tall stair well opening at 27 feet high and lots of ladder climbing is required to maneuver from one floor to the next.

No comments: